10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
These 10 free PSPO I questions are organized by exam domain, so you can see how each part of the Scrum.org Professional Scrum Product Owner I (PSPO I) blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Understanding and Applying the Scrum Framework
Question 1
A new team member states that "transparency" is one of the five Scrum Values. Which response is correct according to the Scrum Guide?
Show answer & explanation
Correct answer: B - Incorrect - transparency is a pillar of empiricism; the value is openness
Domain 2: Developing People and Teams
Question 2
A Product Owner is stretched thin and asks a business analyst to write and refine all Product Backlog items on their behalf. Which statement reflects the Scrum Guide?
Show answer & explanation
Correct answer: A - This is permitted; the Product Owner may delegate the work but remains accountable
Question 3
During a Sprint, a senior executive approaches the Developers directly and instructs them to start work on a feature that is not in the Sprint Backlog. What does the Scrum Guide indicate?
Show answer & explanation
Correct answer: B - Nobody may force the Developers to work from a different set of requirements
Domain 3: Managing Products with Agility
Question 4
In Sprint Planning, the Product Owner proposes how the product could increase its value in the coming Sprint. According to the Scrum Guide, who then defines the Sprint Goal?
Show answer & explanation
Correct answer: D - The whole Scrum Team, collaborating to finalize it before Sprint Planning ends
Question 5
Mid-Sprint, the Developers find that a selected Product Backlog item is much larger than expected. The Sprint Goal is still achievable with a reduced version of the item. What does the Scrum Guide say should happen?
Show answer & explanation
Correct answer: A - Scope may be clarified and renegotiated with the Product Owner as more is learned
Question 6
A Scrum Master tells the Developers they must each answer three set questions in every Daily Scrum: what they did yesterday, what they will do today, and any impediments. What is the most accurate correction?
Show answer & explanation
Correct answer: C - The 2020 Guide prescribes no set questions; the Developers choose the structure
More PSPO I practice questions
Question 7
A Scrum Team completes and integrates three separate Product Backlog items on days 3, 6, and 9 of a two-week Sprint. Each one meets the Definition of Done. How many Increments has the team created?
Show answer & explanation
Correct answer: B - Three - an Increment is born the moment a Product Backlog item meets the Definition of Done
Question 8
A Product Backlog item meets every acceptance criterion the Product Owner wrote for it, but the automated regression suite required by the Scrum Team's Definition of Done has not been run. What is the status of the item?
Show answer & explanation
Correct answer: D - It is not Done and cannot be released or shown at the Sprint Review
Question 9
Under pressure to hit a date, a Product Owner tells the Developers that an item "is a 3-pointer, we have done this before." How should this be judged against the Scrum Guide?
Show answer & explanation
Correct answer: C - Inappropriate - the Developers who will do the work are responsible for the sizing
Question 10
A Scrum Master books a mandatory 90-minute refinement meeting each Sprint and tells the team the Scrum Guide requires refinement to consume up to 10% of the Developers' capacity. What is wrong with this?
Show answer & explanation
Correct answer: D - Refinement is an ongoing activity, not an event, and no capacity figure is prescribed
That's 10 of 1,030
The full bank has 1,020 more PSPO I questions with explanations.